Xionggu Pipeline Automatic Welding Machine Newsletter: The construction of the first lot of the 3rd West East Gas Pipeline has resumed
On January 30, the Xionggu pipeline automatic welding machine service team learned from the project office of the middle section (Zhongwei Ji'an) project (Zhongwei Zaoyang section) of the 3rd West to East gas pipeline that the engineering equipment and construction personnel at the construction site of the first lot of the project have arrived and are now fully resuming work and working hard to catch up with the schedule.
Fig.: Xionggu pipeline automatic welding machine for Xionggu pipeline in the middle section of the 3rd West to East pipeline project
The first lot of the middle section of the 3rdWest to East gas pipeline (Zhongwei Zaoyang) has a total length of 158.22 km, a pipe diameter of 1219 mm, and a design pressure of 10 MPa. The whole line has two sections, passing through Shapotou District, Zhongning County, Tongxin County, Wuzhong City and Pengyang County, Guyuan City. As of February 1, 109.62 kilometers of welding, 87.84 kilometers of corrosion prevention, 65.966 kilometers of trench laying and 53.529 kilometers of backfill have been completed.
“Recommend”
- Xionggu automatic welding machine helps the construction of Zhundong coal-to-gas pipeline project
- Chinese power: Xionggu fully automatic welding machine helps Abu Dhabi West-East Oil Pipeline construction
- The Xionggu automatic welding equipment is about to embark on a new chapter i
- The major Sichuan-East Gas Transmission Project started, Xionggu welding equipment came to help
- Sichuan-East Gas Transmission Line 2 Project Starts, Xionggu Pipeline Automatic Welding Machine Helps Construct Energy Arteries
- Xionggu ultra-low temperature automatic welding equipment
- The quality of Xionggu pipeline automatic welding machine is trustworthy
- Xionggu Pipeline Automatic Welding Equipment Assists the Crossing Project of the South to North Water Diversion Project in Mengxi County
- Xionggu Pipeline Automatic Welding Machine Assists the 2nd lot of directional drilling in the middle section of the 3rd West-East gas pipeline
- Xionggu Pipeline Automatic Welding Machine Participates In The Middle Section of The 3rd West To East Gas Pipeline
【editor】:xiongguCopyright:https://www.xg1992.comReproduced please indicate the source